Fennec Services installed 10 new dwellings — 20 modules across three two-storey buildings — for Ausco Modular in Proserpine. The scope covered crane coordination and module landing, welding and bolting, and full internal and external complexing, together with the supply and installation of second-storey stairs, handrails, balustrades and landings, vertical screens, carports, boardwalks and CFC-clad stairwells. Works were delivered by a crew of up to eight, supported by in-house drafting and project management.
Project highlights
- 10 dwellings
- 20 modules
- 14 weeks on site
- 8 crew at peak